West Lakeview Condo Association

Project:

  • RTU Replacement

Objectives:

  • Replace (15) ton rooftop unit that required substantial repairs. We sought to replace the existing rooftop with an ultra-high efficiency rooftop unit and obtain a ComEd rebate to help offset the cost of the project to the Board of Directors. 

Results:

  • We replaced the rooftop unit and obtained a ComEd rebate in the amount of $9,600. The rebate reduced the replacement cost from $25,028 to $15,428.

Button Line:

  • While saving the owners $9,600, we installed a new unit that reduced electrical consumption by over 25%. The owners also enjoyed extended warranties on the equipment from the manufacturer. 